In response to the text "No work before 2026", "Monteput" did not deny any of the facts that "Vijesti" stated regarding the start of the construction of the second section of the highway from Mateševo to Kolašin.
Instead, it was explained in detail that in 2025 preparatory and preliminary works for the start of construction will begin, geotechnical research and geodetic surveys, construction of access roads to the construction site, formation and construction of camps, formation of testing laboratories, clearing of forests, relocation of installations, development of the main project and necessary studies...
So, all this should be done in 2025, with the main project taking a year (which was announced by "Monteput" to "Vijesta"), so when everything is taken into account, it is clear that the main works ("first phase" ) cannot start before 2026.
In addition, we should not forget that the green light of the European Bank for Reconstruction and Development (EBRD) must be obtained for the environmental impact assessment study, which is a condition for this international financial institution to approve the project.
In sports terms, the team goes out on the field to warm up and prepare, and only then does the match begin.
"Vijesti" is grateful to "Monteput" for explaining in detail in the answer to the question of the editors in which stage the project is and that in the answers to questions on numerous other topics he acts in the same way, while individuals should take account of the public appearances they give space to journalists to debunk their false claims.
Marija Mirjačić