Engineers of the Army of Montenegro have started to remove the temporarily installed bridge in Virpazar.
Since this summer, all traffic has been going over the steel structure, due to the reconstruction of the Velje most.
The removal of the previous parallel road also means that the reconstruction of the Great Bridge is nearing completion, and the installation of lighting remains.
The official opening of the bridge was announced for the Wine and Wine Festival.
The reconstruction began on July 1, 2015 and included the installation of piles and reinforced concrete elements. The contractor is Intermost from Podgorica, the investor is the Directorate of Public Works with 458.000 euros, and the Municipality of Bar financed the project and technical support. The popular Velji Most was built by Prince Nikola in 1905. It is 46 meters long and five meters wide.