The promenade next to Lim almost until next fall

Along with the construction of the coastal fort and promenade, works are being carried out on the construction of the collector

10782 views 30 reactions 4 comment(s)
Work on the construction of the promenade in progress, Photo: Jadranka Ćetković
Work on the construction of the promenade in progress, Photo: Jadranka Ćetković
Disclaimer: The translations are mostly done through AI translator and might not be 100% accurate.

One of the most significant projects in Bijelo Polje, the coastal fortress with a modern promenade on Lim, will be able to receive the first walkers in the fall of next year.

The complete project worth 4,5 million euros is financed by the World Bank. In parallel, in the trunk of the promenade, as told to "News" from the Municipality, a collector for the purification of waste water is already connected, which will collect all fecal drains from the city center, which will greatly contribute to the reduction of pollution in Lima.

"The people of Bjepoloj are looking forward to the promenade, so one of the 'obligatory' outings for many of them has become a tour and monitoring of the works, especially before the shores of Lim have become almost inaccessible to citizens due to decades of neglect. By building a modern promenade with a fishing, walking and cycling path, a modern ambient unit will be created, which will completely transform the appearance of Bijelo Polje, because it will open onto the river", announced the Municipality.

The flow of work was also one of the councilor's questions at the SO session, which was brought up to date by the councilwoman Jasmila Hot.

"With the completion of this work, Bijelo Polje will have a modern promenade with a length of 650 meters, and the deadline for the completion of the works is 18 months. According to the reports of the contractors and supervisory authorities, the work on this project is progressing according to plan," said the secretary of the Secretariat for Construction. Mensur Hajdarpašić.

He explained to "Vijesti" that the project also envisages the construction of a bicycle path, and that the promenade will have two levels, the first three meters wide and the second six meters wide.

"Along with the construction of the coastal fort, works are being carried out on the construction of the 450-meter-long collector. The value of these works is 220.000 euros, and the contractor is the company "Nikos cop" from Beran. This project envisages that all fecal sewage that is currently in this part will be connected to the new collector, and it will go all the way to the Health Center and Plavi Most, where it will be connected to the pumping station", he said, adding that with the construction of the planned coastal fortifications, parts of the settlement along the river Lim to be permanently protected from floods, providing the population with useful areas for various recreational activities.

The contractor is the Serbian "Kolubara and HSV Consortium".

When it comes to the valorization of the capital projects of the ski center "Cmiljača" and the Đalovića cave, Hajdarpašić, in the answer to the councilor Asmir Pućurica stated that the secretariat headed by him carried out the project assignment for the reconstruction of the road Jasikovac-base settlement Cmiljača according to the design-build system, which was submitted together with the urban planning and technical conditions to the Directorate for Capital Projects, where they expect a tender for the design and execution of the works to be announced .

"Regarding the water supply of service facilities at the location of the mountain center of Cmiljač, the Administration is working on amending the project documentation which will be aligned with the current legislation, after the amendment of the project documentation and resolved property-legal relations, a tender for the selection of the contractor will be announced," he said. Hajdarpašić.

Regarding the Đalovića cave project, he explained that a tender is underway for the preparation of a remediation study in the interior of the cave, and a tender for a transmission line with a service access road and a substation at the Đalovići site was announced, which was canceled because no bids were received.

"The contractor for the construction of the cable line for the power supply of the Visitoring Center has been selected. When it comes to the water supply of the entrance to Đalovića Cave and the service facilities, the Secretariat has submitted the project assignment and urban planning and technical conditions based on which the Capital Projects Administration will call for a tender for the execution of the works," said Hajdarpašić.