Castle and park locked for two seasons: "Unforeseen circumstances" delayed reconstruction

Works on the Homeland Museum are almost a year behind schedule and have exceeded one million euros due to several newly discovered finds made during the reconstruction.

13190 views 2 comment(s)
King Nikola's Castle in Bar, Photo: Marija Pešić
King Nikola's Castle in Bar, Photo: Marija Pešić
Disclaimer: The translations are mostly done through AI translator and might not be 100% accurate.

The Bar Heritage Museum, the former King Nikola's Castle, and its park have been closed for the second summer season due to reconstruction. The completion of the works is almost a year behind schedule, and newly discovered traces of wall paintings, among other things, have raised the cost of the project to more than a million euros.

The reconstruction of the former King Nikola's Castle in Topolica has been underway since November 2023, XNUMX. The original plan was for it to last nine months, but "unforeseen circumstances" have prolonged the process, and completion is expected by the end of this year.

Although the gates of one of the most visited parks and museums in Bar are locked this tourist season, the local administration's position is that it is better to carry out the reconstruction comprehensively and with quality, rather than partially and inadequately.

Conservation works are currently being carried out on the interior of the building and on the technical installations. Due to several newly discovered findings made during the works, the most important of which is the static instability of certain parts of the structure, it was necessary to prepare a revised and amended main and conservation project, without which the works would not make sense.

King Nikola's Castle in Bar
King Nikola's Castle in Barphoto: Marija Mirjačić

"Vijesti" was told this by the Municipality of Bar and emphasized that it should be borne in mind that this is the first complete and comprehensive reconstruction and conservation of the facility, which was approached in this way due to the historical and cultural significance it has for Bar and Montenegro.

As part of the project, the part of the work related to the dismantling of floor and wall layers, the production of completely new exterior joinery, the repair of the roof structure, the replacement of installations, the cleaning and restoration of the locksmithing in the ballroom, the plastering and smoothing of the ceiling and walls, and the restoration of part of the floors have been completed.

Next comes work on stabilizing the structure, installing floors, interior joinery, final work on the walls and complete restoration of the building's facade, reconstruction of the guard towers, laboratories and furnishing the building's interior.

"Due to the specific status and condition of the building, which is an immovable cultural asset of Montenegro, the project could not foresee all the necessary works, because many discoveries were made only after the start of the works and the removal of layers of floor and wall coverings, which is why a modified project was developed and the works were partially halted," said the local administration that finances and manages this project. Dušan Raičević.

The contracted deadline for completion of the works is six months from the introduction of the contractor into work according to the amended and supplemented main project, or by the end of the current year.

"After the completion of all works, Bar will receive an exceptional and representative space, primarily the Homeland Museum, as well as a much higher quality space for holding cultural and public programs," the local government emphasized.

Director of the Cultural Center, which is responsible for the Homeland Museum, Aleksandra Grabež, said at the previous session of the Bar Municipal Assembly that the works were extended and the plan changed due to newly discovered traces of wall painting.

The Municipality explained that by removing layers of walls during reconstruction, various layers from previous periods were discovered, some of which represent valuable examples of wall painting, and their protection, conservation and presentation were appropriately planned in the aforementioned amended project.

When asked why these valuable elements of the mural painting were not previously known to the management of the Cultural Center, they did not answer.

Such unforeseen circumstances during the reconstruction and conservation are the reason for the development of a revised project and an increase in the scope of work on the facility, in order to carry out all necessary work that will bring the facility into a functional and safe condition for future use.

"This is primarily the static stabilization of the slab above the ballroom and the reconstruction of the open terrace above it, the complete reconstruction of the guard towers, the production of floor coverings, wall and ceiling decorations modeled after the original ones, as well as the furnishing of the interior for adequate presentation of museum exhibits," the Bar municipality said in its responses.

The total value of construction and conservation works, including works on the interior decoration of the building, amounts to almost 910 thousand euros. The tender for the "supplementary" works was announced on the last day of the previous year.

The value of the works envisaged by the amendments to the Main Revised Design with interior design, for two segments (interior design equipment and construction works) is 920.000 euros.

756.000 euros are earmarked for construction works (reconstruction), while 164.000 euros are earmarked for interior decoration. The value of VAT is 193,2 thousand euros. The primary funds planned for this project are around 870 thousand euros.