The state-owned Montenegrin Electricity Distribution System (CEDIS) announced that the allegations by the Podgorica Construction and Development Agency that work on the construction site of the multifunctional facility in Zagorič was slowed down because the construction site connection to CEDIS was awaited for more than eight months are incorrect.
They stated this in response to the Agency's statements in the article "Return to the construction site in Zagorič by the end of the month", published yesterday on the Vijesti portal.
"Upon the request of 'Gradnja Promet' doo, number 30-20-02-8145 dated 12.08.2024, a Contract was concluded on the construction of infrastructure for connection and connection, for a construction site connection for the needs of the construction of a Multifunctional facility in the Zagorič settlement, KP 586/1, 586/2, 586/4, 586/5, 586/6, 586/7, 587/2, 587/3, KO Podgorica II, number 30-20-02-8472 dated 21.08.2024. 'Gradnja Promet' doo submitted to CEDIS a notification on the fulfillment of contractual obligations number 30-20-02-8671 dated 29.08.2024. Upon the submitted notification, CEDIS installed a measuring device-meter, on "On September 10, 2024, and delivered to the applicant the Notice of Fulfillment of Contractual Obligations for the Purpose of Concluding the Supply Contract No. 30-20-02-9060 dated September 12, 2024," the response reads.
They said that it is easy to conclude from the attached documents that CEDIS fulfilled its obligations in the process of connecting the construction site connection in question promptly and that the allegations that it caused delays in the work on the facility are unfounded.
See more:
Download the app and follow the news
FOLLOW US ON