A step towards building a regional center: Bar seeks contractor for animal waste incinerator worth 250.000 euros

It is planned that the Kufin facility will be able to process up to 2,5 tons of waste per day, and bids are due by October 16th.

Disposal of animal by-products is one of the issues related to fulfilling the conditions for closing the negotiation Chapter 12 - Food Safety, Veterinary and Phytosanitary Control

5624 views 0 comment(s)
It is necessary to solve the problem of dead animals (illustration), Photo: Shutterstock
It is necessary to solve the problem of dead animals (illustration), Photo: Shutterstock
Disclaimer: The translations are mostly done through AI translator and might not be 100% accurate.

The Municipality of Bar has announced a tender worth 250.000 euros excluding VAT for the design and construction of a facility in which dead animals and slaughterhouse waste from the territory of that municipality will be burned in a controlled manner.

The incinerator is planned for Kufin and is planned to be able to process about 2,5 tons of animal waste per day.

This is a "design and build" system, which means that the future contractor, who is selected in the tender, is not only expected to deliver and install the incinerator, but also to develop the main project and supporting documentation.

The tender also includes a prefabricated building with an area of ​​100 square meters, with a crane for lifting the lid and loading containers with a capacity of 3,5 tons.

President of the Municipality of Bar Dušan Raičević On June 22, it issued a decision determining the location and defining the basic urban planning and technical conditions at the request of the Bar-based DOO “Lovstvo”.

According to this decision, not only an incinerator is planned, but also a utility-service complex for the collection, reception, storage, processing and final disposal of animal by-products not intended for human consumption. The plan includes a reception plateau, cold chambers and closed containers, a technological line for thermal treatment, wastewater and emissions treatment systems, storage capacities, as well as accompanying administrative and technical facilities.

The municipality also specified that the facility must be designed to prevent the spread of infectious diseases and enable the control of unpleasant odors, emissions and noise, as well as the protection of surface and groundwater. The documentation also provides for controlled access to the facility and supervision of the entry and exit of materials.

A more detailed layout of the future incinerator was defined in the project terms of reference of DOO “Lovstvo” dated August 27, and then in the tender documentation.

Other municipalities are also counting on the incinerator

The construction of the plant in Bar has a significance that goes beyond the needs of that municipality and a local issue, because adequate disposal of animal by-products is one of the issues related to fulfilling the conditions for closing the negotiating Chapter 12 - Food Safety, Veterinary and Phytosanitary Surveillance.

As "Vijesti" previously wrote, Montenegro was supposed to provide livestock cemeteries in all municipalities by May 1st of this year as a temporary solution, but a large number of local governments failed to designate appropriate plots, so the Government is considering regional solutions and mobile incinerators so that the problem does not slow down European integration.

Bar stands out in these plans because, according to "Vijesti", it is the only municipality that has already entered the process of purchasing an incinerator, and the future plant is also envisioned as a regional solution for the Montenegrin coast.

The Royal Capital of Cetinje is directly counting on Bar, which previously announced to the editorial staff that it would solve the problem of disposing of dead livestock together with the municipalities of Bar and Budva, with Bar coordinating the work and providing conditions for the treatment of dead animals.

Herceg Novi is also counting on a regional solution, as it has not determined a location for a livestock cemetery and, after discussions with the Government, pointed out the need for cooperation between several coastal municipalities and a joint location that would serve the needs of several cities. This is supported by Government documentation, which also counts on the Bar incinerator as part of solving the problem of animal waste disposal.

Up to 2,5 tons per day

The plant is planned to process up to 2.500 kilograms of waste in approximately ten to twelve hours a day. The incinerator itself should be at least three meters long, 1,3 meters wide and 4,4 meters high, weigh at least 5,5 tons, with a chamber volume of about 1,9 cubic meters. The specification lists a burning rate of up to 200 kilograms per hour and a maximum operating temperature of 1.320 degrees, and it is estimated that about three percent of ash would remain after the process.

The procurement also prescribes emission limit values: 30 milligrams of dust per cubic meter, 200 milligrams of sulfur dioxide, 400 milligrams of nitrogen dioxide, and 100 milligrams of carbon monoxide.

Potential bidders had doubts about the technical requirements, the documentation shows, because they approached the Municipality, among other things, with questions about the dimensions and volume of the chamber, temperatures, burning speed, standards, emissions and the method of proving certain characteristics. The Commission responded that the stated dimensions, mass, chamber capacity and temperature range represent minimum and functional requirements, and not characteristics of a particular manufacturer.

The bidders' questions led to changes to certain tender conditions, so the request for the engagement of an electrical engineer for electronic communications was removed from the documentation, while the Municipality maintained the request for the engagement of an architect, explaining that he would be needed for the terrain development phase.

Price carries 80 out of 100 points

When selecting a contractor, price will have the greatest weight - 80 out of a total of 100 points, while the remaining 20 are allocated to the deadline for completing the work.

This part of the tender was also changed after questions from interested bidders, and the final changes determined that the execution period cannot be shorter than 120 or longer than 180 calendar days after the completion and submission of the main project. The contractor will have 30 days from the conclusion of the contract to prepare the main project itself.

The deadline scoring formula was also changed so that shorter proposed execution times would earn more points. The changes came after questions indicated that the original formula practically favored longer deadlines, even though deadlines were designated as a quality criterion.

In addition to other requirements, participation requires a bid guarantee of two percent of the estimated procurement value, or 5.000 euros, and the bid is valid for 120 days from the opening.

The contract also provides for an advance payment: the Municipality will pay 50 percent of the contracted amount to the selected contractor within three days of signing the contract, while the other half will be paid within 30 days of submitting the completed situation. A warranty period of 12 months from the start of operation is provided for the works and the plant.

After several questions, clarifications and changes during September, the Municipality, with the last change of September 29, postponed the deadline for submitting bids - until October 16 at 11 am, when their opening is also scheduled.